buy-out funnel — Packages → RFQs → POs → Deliveries. At-risk callouts surface stalled scope, late tenders, overdue POs, and missing-on-site deliveries.
| Code | Name | Stage | Contract value | Pipeline | Age |
|---|---|---|---|---|---|
| PKG-BMS | BMS, security & comms | Planning | — | 0/0/0 | 10d |
| PKG-BRICK-ARCH | Brick & block work (architectural) | Planning | — | 0/0/0 | 10d |
| PKG-BRICK-LB | Brick & block work (load-bearing) | Planning | — | 0/0/0 | 10d |
| PKG-CIVIL | Civil works (external) | Planning | — | 0/0/0 | 10d |
| PKG-CONC-STR | Concrete & reinforcement (structural) | Planning | — | 0/0/0 | 10d |
| PKG-CONC-SUS | Concrete & reinforcement (suspended) | Planning | — | 0/0/0 | 10d |
| PKG-DEMO | Demolition | Planning | — | 0/0/0 | 10d |
| PKG-DOORS | Doors & hardware | Planning | — | 0/0/0 | 10d |
| PKG-ELEC | Electrical services | Planning | $1,220,000 | 0/0/0 | 10d |
| PKG-ESTAB | Site establishment, hoarding & signage | Delivered | — | 0/1/1 | 10d |
| PKG-EXCAV | Bulk excavation & spoil cartage | Planning | — | 0/0/0 | 10d |
| PKG-FACADE | Facade & curtain wall | RFQ awarded | $2,980,000 | 2/1/0 | 10d |
| PKG-FIRE | Fire services (hydrants, sprinklers, detection) | Planning | — | 0/0/0 | 10d |
| PKG-FLOOR | Floor finishes (tile, vinyl, carpet) | Planning | — | 0/0/0 | 10d |
| PKG-FRAME | Structural frame & concrete | Delivering | $4,850,000 | 0/2/0 | 10d |
| PKG-HYD | Hydraulic services | RFQ out | — | 1/0/0 | 10d |
| PKG-JOIN | Joinery & millwork | Planning | — | 0/0/0 | 10d |
| PKG-LAND | Landscaping & soft works | Planning | — | 0/0/0 | 10d |
| PKG-LIFT | Lifts & vertical transport | Planning | — | 0/0/0 | 10d |
| PKG-MECH | Mechanical services | PO issued | $1,640,000 | 1/1/0 | 10d |
| PKG-PAINT | Painting & decorative finishes | RFQ awarded | — | 1/0/0 | 10d |
| PKG-PART | Internal partitions & linings | Planning | — | 0/0/0 | 10d |
| PKG-PAVE | Hardstands & paving (external) | Planning | — | 0/0/0 | 10d |
| PKG-PILE | Piling | Planning | — | 0/0/0 | 10d |
| PKG-PLUMB | Plumbing & drainage | Planning | — | 0/0/0 | 10d |
| PKG-ROOF | Roofing & waterproofing | RFQ out | — | 1/1/0 | 10d |
| PKG-SITE | Site management & preliminaries | Planning | $980,000 | 0/1/0 | 10d |
| PKG-STEEL | Structural steel | Planning | — | 0/0/0 | 10d |
| PKG-STORM | Stormwater & sewer (external) | Planning | — | 0/0/0 | 10d |