Immutable record of state-changing actions across the operator's tenant. Showing the most recent 3 events. Tenant-scoped via row-level security.
| When | Actor | Project | Entity | Action | Summary |
|---|---|---|---|---|---|
| 02 June, 11:54 am | Local Dev User | DEMO-1 | rfi RFI-019 | status_transition | RFI closed · cost impact no · schedule impact yes |
| 02 June, 11:52 am | Local Dev User | DEMO-1 | rfi RFI-019 | update | RFI manager set to user a0eebc99-9c0b-4ef8-bb6d-6bb9bd380a11 |
| 02 June, 11:52 am | Local Dev User | DEMO-1 | rfi RFI-019 | create | RFI-019 raised - E2E TEST - Grid line A/B drawing discrepancy (formal UAT) (from template) |
Audit coverage closed by Phase 4. New mutations via the variation actions append here automatically; claim + HSEQ writers wire in next as those flows ship more transitions.