Opened 2/6/26, 12:07 pm by Local Dev User
E2E TEST - Please relocate the fire hydrant booster assembly from grid B3 to grid C4 per the latest hydraulic coordination markup. Confirm receipt and program impact.
E2E TEST - Reply: Instruction received. Booster relocation to grid C4 acknowledged; minor 2-day program impact expected. Proceeding.