AUDIT RERUN: EWP commissioning rev D adds two additional lift-off chain pull-tests at the level 3 east edge (gridlines 4/B and 5/B). Test load 2.5x SWL, witness by client structural engineer. ROM cost covers crane mob, pull-test rig hire, and a half-day witness. Test record only.
Change event/#7
AUDIT RERUN: EWP commissioning rev D adds two additional lift-off chain pull-tests at the level 3 east edge (gridlines 4/B and 5/B). Test load 2.5x SWL, witness by client structural engineer. ROM cost covers crane mob, pull-test rig hire, and a half-day witness. Test record only.