Proactive watchdog feed for DEMO-1. Suggestions are evidence-cited — every reference resolves to a real record. Live Claude calls activate when assistant.enabled is on.
Routes through the full chain: preflight cost caps, Claude call, postflight evidence checks. Responses cite record ids or explicitly say they have no evidence.
Per §30.9 the Assistant flags CP tasks behind progress as programme risk.
Proposed: Open Schedule, review CP tasks, capture recovery plan in PM checklist.
"Footing reinforcement detail clarification" has no formal response and is past its due date. §11.1 says open RFIs should have draft responses within 2h.
Proposed: Open the RFI, draft an official response from drawings + prior RFIs, post for review.
"Facade bracket tolerance query" has no formal response and is past its due date. §11.1 says open RFIs should have draft responses within 2h.
Proposed: Open the RFI, draft an official response from drawings + prior RFIs, post for review.
"Hydraulic riser penetration offsets" has no formal response and is past its due date. §11.1 says open RFIs should have draft responses within 2h.
Proposed: Open the RFI, draft an official response from drawings + prior RFIs, post for review.
"Electrical switchboard room ventilation" has no formal response and is past its due date. §11.1 says open RFIs should have draft responses within 2h.
Proposed: Open the RFI, draft an official response from drawings + prior RFIs, post for review.
"Landscape edge restraint detail" has no formal response and is past its due date. §11.1 says open RFIs should have draft responses within 2h.
Proposed: Open the RFI, draft an official response from drawings + prior RFIs, post for review.
"Architectural ceiling setout conflict" has no formal response and is past its due date. §11.1 says open RFIs should have draft responses within 2h.
Proposed: Open the RFI, draft an official response from drawings + prior RFIs, post for review.
"Structural grout strength acceptance criteria" has no formal response and is past its due date. §11.1 says open RFIs should have draft responses within 2h.
Proposed: Open the RFI, draft an official response from drawings + prior RFIs, post for review.
"Floor covering discrepency" has no formal response and is past its due date. §11.1 says open RFIs should have draft responses within 2h.
Proposed: Open the RFI, draft an official response from drawings + prior RFIs, post for review.
"[AUDIT 05-302133] RFI subject" has no formal response and is past its due date. §11.1 says open RFIs should have draft responses within 2h.
Proposed: Open the RFI, draft an official response from drawings + prior RFIs, post for review.
"[AUDIT 05-302134] RFI subject" has no formal response and is past its due date. §11.1 says open RFIs should have draft responses within 2h.
Proposed: Open the RFI, draft an official response from drawings + prior RFIs, post for review.
"[AUDIT 05-302136] RFI subject" has no formal response and is past its due date. §11.1 says open RFIs should have draft responses within 2h.
Proposed: Open the RFI, draft an official response from drawings + prior RFIs, post for review.
Official response is published; capture cost/schedule impact and close per §30.3.
Proposed: Tick impact flags, add a close note, click Close.
Official response is published; capture cost/schedule impact and close per §30.3.
Proposed: Tick impact flags, add a close note, click Close.
Official response is published; capture cost/schedule impact and close per §30.3.
Proposed: Tick impact flags, add a close note, click Close.
Multiple revisions issued. Per §30.4 the Assistant scans rev → rev geometry/scope deltas for variation candidates.
Proposed: Open the drawing in compare mode and check for scope deltas.
Multiple revisions issued. Per §30.4 the Assistant scans rev → rev geometry/scope deltas for variation candidates.
Proposed: Open the drawing in compare mode and check for scope deltas.
Multiple revisions issued. Per §30.4 the Assistant scans rev → rev geometry/scope deltas for variation candidates.
Proposed: Open the drawing in compare mode and check for scope deltas.
Multiple revisions issued. Per §30.4 the Assistant scans rev → rev geometry/scope deltas for variation candidates.
Proposed: Open the drawing in compare mode and check for scope deltas.
Multiple revisions issued. Per §30.4 the Assistant scans rev → rev geometry/scope deltas for variation candidates.
Proposed: Open the drawing in compare mode and check for scope deltas.
Multiple revisions issued. Per §30.4 the Assistant scans rev → rev geometry/scope deltas for variation candidates.
Proposed: Open the drawing in compare mode and check for scope deltas.
Multiple revisions issued. Per §30.4 the Assistant scans rev → rev geometry/scope deltas for variation candidates.
Proposed: Open the drawing in compare mode and check for scope deltas.
Multiple revisions issued. Per §30.4 the Assistant scans rev → rev geometry/scope deltas for variation candidates.
Proposed: Open the drawing in compare mode and check for scope deltas.
Multiple revisions issued. Per §30.4 the Assistant scans rev → rev geometry/scope deltas for variation candidates.
Proposed: Open the drawing in compare mode and check for scope deltas.
Multiple revisions issued. Per §30.4 the Assistant scans rev → rev geometry/scope deltas for variation candidates.
Proposed: Open the drawing in compare mode and check for scope deltas.
SVAR-001 has had no negotiation exchange in 10d. Per §30.6 the next-turn cadence is 5d. Proposed action: Nudge owner.
Proposed: SVAR-001 has had no negotiation exchange in 10d. Per §30.6 the next-turn cadence is 5d. Proposed action: Nudge owner.
RFI #3 was due 3d ago and still has no formal response. §11.1 says open RFIs should have a draft response within 24h. Proposed action: Nudge owner.
Proposed: RFI #3 was due 3d ago and still has no formal response. §11.1 says open RFIs should have a draft response within 24h. Proposed action: Nudge owner.
VAR-008 has had no negotiation exchange in 5d. Per §30.6 the next-turn cadence is 5d. Proposed action: Nudge owner.
Proposed: VAR-008 has had no negotiation exchange in 5d. Per §30.6 the next-turn cadence is 5d. Proposed action: Nudge owner.
VAR-007 has had no negotiation exchange in 5d. Per §30.6 the next-turn cadence is 5d. Proposed action: Nudge owner.
Proposed: VAR-007 has had no negotiation exchange in 5d. Per §30.6 the next-turn cadence is 5d. Proposed action: Nudge owner.
Claim PC-003 submitted 10d ago under NSW SOPA; no payment schedule received. SOPA windows are tight — chase before adjudication risk. Proposed action: Nudge owner.
Proposed: Claim PC-003 submitted 10d ago under NSW SOPA; no payment schedule received. SOPA windows are tight — chase before adjudication risk. Proposed action: Nudge owner.
RFI #11 was due 1d ago and still has no formal response. §11.1 says open RFIs should have a draft response within 24h. Proposed action: Nudge owner.
Proposed: RFI #11 was due 1d ago and still has no formal response. §11.1 says open RFIs should have a draft response within 24h. Proposed action: Nudge owner.
VAR-006 has had no negotiation exchange in 5d. Per §30.6 the next-turn cadence is 5d. Proposed action: Nudge owner.
Proposed: VAR-006 has had no negotiation exchange in 5d. Per §30.6 the next-turn cadence is 5d. Proposed action: Nudge owner.
VAR-005 has had no negotiation exchange in 5d. Per §30.6 the next-turn cadence is 5d. Proposed action: Nudge owner.
Proposed: VAR-005 has had no negotiation exchange in 5d. Per §30.6 the next-turn cadence is 5d. Proposed action: Nudge owner.
VAR-004 has had no negotiation exchange in 5d. Per §30.6 the next-turn cadence is 5d. Proposed action: Nudge owner.
Proposed: VAR-004 has had no negotiation exchange in 5d. Per §30.6 the next-turn cadence is 5d. Proposed action: Nudge owner.
Claim PC-001 submitted 10d ago under NSW SOPA; no payment schedule received. SOPA windows are tight — chase before adjudication risk. Proposed action: Nudge owner.
Proposed: Claim PC-001 submitted 10d ago under NSW SOPA; no payment schedule received. SOPA windows are tight — chase before adjudication risk. Proposed action: Nudge owner.
RFI #15 was due 1d ago and still has no formal response. §11.1 says open RFIs should have a draft response within 24h. Proposed action: Nudge owner.
Proposed: RFI #15 was due 1d ago and still has no formal response. §11.1 says open RFIs should have a draft response within 24h. Proposed action: Nudge owner.
RFI #1 was due 1d ago and still has no formal response. §11.1 says open RFIs should have a draft response within 24h. Proposed action: Nudge owner.
Proposed: RFI #1 was due 1d ago and still has no formal response. §11.1 says open RFIs should have a draft response within 24h. Proposed action: Nudge owner.
RFI #14 was due 1d ago and still has no formal response. §11.1 says open RFIs should have a draft response within 24h. Proposed action: Nudge owner.
Proposed: RFI #14 was due 1d ago and still has no formal response. §11.1 says open RFIs should have a draft response within 24h. Proposed action: Nudge owner.
RFI #13 was due 1d ago and still has no formal response. §11.1 says open RFIs should have a draft response within 24h. Proposed action: Nudge owner.
Proposed: RFI #13 was due 1d ago and still has no formal response. §11.1 says open RFIs should have a draft response within 24h. Proposed action: Nudge owner.
RFI #12 was due 1d ago and still has no formal response. §11.1 says open RFIs should have a draft response within 24h. Proposed action: Nudge owner.
Proposed: RFI #12 was due 1d ago and still has no formal response. §11.1 says open RFIs should have a draft response within 24h. Proposed action: Nudge owner.
VAR-002 has had no negotiation exchange in 5d. Per §30.6 the next-turn cadence is 5d. Proposed action: Nudge owner.
Proposed: VAR-002 has had no negotiation exchange in 5d. Per §30.6 the next-turn cadence is 5d. Proposed action: Nudge owner.
RFI #8 was due 2d ago and still has no formal response. §11.1 says open RFIs should have a draft response within 24h. Proposed action: Nudge owner.
Proposed: RFI #8 was due 2d ago and still has no formal response. §11.1 says open RFIs should have a draft response within 24h. Proposed action: Nudge owner.
RFI #5 was due 1d ago and still has no formal response. §11.1 says open RFIs should have a draft response within 24h. Proposed action: Nudge owner.
Proposed: RFI #5 was due 1d ago and still has no formal response. §11.1 says open RFIs should have a draft response within 24h. Proposed action: Nudge owner.