IDC Construct Building & Construction · ABN 00 000 000 000
PC-001 Payment claim
Project 004-MIRA · Mira Living
Issued 4 June 2026
Reference date 4 June 2026

Progress payment claim PC-001

submitted Head contractor to Principal SOPA NSW
SOPA NSW statutory header This is a payment claim made under the Building and Construction Industry Security of Payment Act 1999 (NSW). Reference date: 2026-06-04.

Claim details

Reference
PC-001
Side
Head contractor to Principal
Jurisdiction
NSW
Reference date
4 June 2026
Status
submitted

Project

Code
004-MIRA
Name
Mira Living
Currency
AUD

Schedule of values

LineAmount
Claimed this period (ex GST)$485,000
Certified to date (ex GST)$0
Retention held this period$24,250
Paid to date$0
Net certified (ex GST)$-24,250
GST on net certified (10%)$-2,425
Net certified inc GST$-26,675
Balance due (certified less paid, ex GST)$0

SOPA cycle (statutory deadlines)

MilestoneDateAmount
Reference date4 June 2026
Claim issued4 June 2026$485,000
Payment schedule due by18 June 2026
Payment schedule amountnot set
Payment due by25 June 2026

Statutory declaration

The Claimant declares that all employees, subcontractors and suppliers have been paid all amounts due and payable in respect of work covered by this payment claim, in accordance with the relevant Building and Construction Industry Security of Payment Act.

Signatures

Claimant authorised signatory Print name Date: __________________
Witness Print name Date: __________________